Beautiful Virgin Islands

Wednesday, May 13, 2026

Ex FS Neil M. Smith under fire; Conflict of interest role

Ex FS Neil M. Smith under fire; Conflict of interest role

Mr Smith made decisions to dole out Taxpayers’ funds outside of what Cabinet agreed to!

As residents continue to read the Auditor General Ms Sonia M. Webster’s damning report on the ‘Government‘s Financing of the BVI Airways’ Direct Flights to Miami’ project, more revelations are being unearthed.


The report shows that after an agreement, whereby Government had promised an investment of $7.0M and the Operator parties to put in their own $6.0 M, taxpayers were left holding the bag after over $7.2M was paid out and there were no flights, no plane, no information of the Operator parties’ $6.0M and no return of taxpayers $7.2M.

In her report, the Auditor General also showed how the former Financial Secretary (FS), Mr Neil M. Smith, allegedly facilitated this scam on the people of the Virgin Islands.


No letter of credit no deal?

The Operator parties had demanded a ‘Letter of Credit’ from the then National Democratic Party (NDP) Government headed by former Premier Dr D. Orlando Smith.

The government was unable to produce the Letter of Credit secured by taxpayers; therefore, the former FS Smith used that as a reason to dole out some $7.2M in less than one year, which was a violation of the payment schedule of three years.

In the Auditor General’s Report, on page 11 No. 45, she noted that Mr Smith stated it was difficult for the Dr Smith regime to secure a Letter of Credit because “stringent regulatory requirements in the banking industry that were resulting in large scale derisking …as a result obtaining a letter of credit would be possible but costly.”

Mr Smith, in his decision to violate Cabinet’s payment schedule, used this argument to dole out some $500,000 some 9 days ahead of the first payment schedule in January 2016, weeks after the Framework Agreement was agreed to by Cabinet.

If that was not enough, less than two months later, again in violation of Cabinet’s Framework Agreement Payment Schedule, Mr Smith paid out another $2.4M two months ahead of schedule.


Treasury was BVI Airways' piggy bank

The BVI Airways Operator parties seemed to have used public funds as their ‘piggy bank’ for the project and by October and November 2016, a full two years ahead, the former FS paid yet again two amounts totaling $2.1M, according to the report on page 11 No. 47.

By November of 2016, BVI Airways had collected $5.0M without a sign of an aircraft and no approval from US Department of Transportation or the local regulator Air Safety Support International (ASSI), according to the report on page 52 No. 55, which stated that these approvals lasted more than a “year and a half.”

The Framework Agreement, signed by both Government and the Operator parties, stipulated that the final $2.0M was to be paid only after the BVI-Miami air service was successfully launched as per page 11 No. 48 of the report.


Former FS Smith gave up all the money with nothing to show

Eager to get the government’s full $7.0M on June 6, 2016; however, both parties executed an addendum that provided for the remaining $2.0M to be placed into an escrow account with a new payment schedule of May 30, 2017, when $1,200,000 was to be paid and November 30, 2017, when $800,000 was to be paid, according to the report on page 11 No. 46.

If that was not enough, the Operator parties demanded, and it was agreed to by the Dr Smith Government, of a new and additional amount of money beyond the Cabinet approved $7.0M.

In the same addendum to the Framework, “an additional $200,000, allegedly to compensate the cost associated with the delays of the Government’s failure to produce the Letter of Credit was agreed to; however, contrary to the rules on Government spending the parties provided no supporting information or evidence to substantiate their claim for the additional funds,” according to page 12 No. 50 of the report.


Outside of the $7M and $200,000 was paid out

The report noted that “the $200,000 was paid to BVI Airways on August 26, 2016, on the faith of their unsupported claim.”

After BVI Airways received the extra $200,000 wired out to them less than a month after the addendum to the Payment Schedule (no one has included the cost to taxpayers of the wire charges), the former FS Smith- as per the report on page 12 No. 53- “terminated the escrow arrangement and authorised release of the funds to the Operator parties on January 11, 2017, way before the new payment date and giving the Operator parties well over $7.2M before they even had approval from the UK and USA regulatory authorities to fly between Beef Island and Miami,” according to the Auditor General on page 12 No. 55.

The Auditor General, Ms Webster, concluded that Mr Smith did this without any binding financial commitment from the Operator parties or penalties for failing to provide financing, therefore the Operator parties relied almost exclusively on the money provided by the government, as stated on page 15 No. 75.


Conflict of Interest; no one looking out for taxpayers

The Auditor General raised some serious concerns about Mr Smith’s, the former FS, role in the BVI Airways project. She noted “the assignment of the Financial Secretary to facilitate the venture eliminated an important checklist that should exist between project execution and project financing. This created a conflict whereby the Financial Secretary’s obligation to ensure the successful launching of the project may have obscured his public duty as primary custodian of Government’s finances. The acute level of scrutiny that should have been applied to the financial and other issues of risk presented by the Operator parties was replaced with insistent action to accommodate their requests,” according to page 18 No. 98.

In another scathing rebuke of the former Financial Secretary’s role in the BVI Airways’ scandal, the Auditor General noted in her report on page 18 No. 99 that the project did not undergo the necessary financial scrutiny, “instead it was flawed by early payments without Cabinet authorisation."

Newsletter

Related Articles

Beautiful Virgin Islands
0:00
0:00
Close
The Great Western Exit: Why Best Citizens Are Fleeing the Rich World [PODCAST]
The New Robber Barons of Intelligence: Are AI Bosses More Powerful Than Rockefeller?
The End of the Old Order [Podcast]
Britain’s Democracy Is Now a Costume
The AI Gold Rush Is Coming for America’s Last Open Spaces [Podcast]
The Pentagon’s AI Squeeze: Eight Tech Giants Get In, Anthropic Gets Shut Out [Podcast]
The War Map: Professor Jiang’s Dark Theory of Iran, Trump, China, Russia, Israel, and the Coming Global Shock [Podcast]
Labour Is No Longer a National Party [Podcast]
AI Isn’t Stealing Your Job. It’s Dismantling It Piece by Piece.
Lawyers vs Engineers: Why China Builds While America Litigates [Podcast]
Churchill’s Glass: The Drunk, the Doctor, and the Myth Britain Refuses to Sober Up From
Apple issues an unusual warning: this is how your iPhone can be hacked without you doing anything
The Met Gala Meets the Age of Billionaire Backlash
Russian Oligarch’s Superyacht Crosses Hormuz via Iran-Controlled Route
Gunfire Disrupts White House Correspondents’ Dinner as Trump Is Evacuated
A Leak, a King, and a Fracturing Alliance
Inside the Gates Foundation Turmoil: Layoffs, Scrutiny, and the Cost of Reputational Risk
UK Biobank Breach Exposes Health Data of 500,000, Listed for Sale on Chinese Platform
KPMG Cuts Around 10% of US Audit Partners After Failed Exit Push
French Police Probe Suspected Weather-Data Tampering After Unusual Polymarket Bets on Paris Temperatures
News Roundup
Microsoft lost 2.5 millions users (French government) to Linux
Privacy Problems in Microsoft Windows OS
News roundup
Péter András Magyar and the Strategic Reset of Hungary
Hungary After the Landslide — A Strategic Reset in Europe
×