A report on the various contracts executed between the Virgin Islands Party (VIP) government and Claude Skelton-Cline after 2019 has been completed by the Auditor General.
This is according to the latest update from the
Commission of Inquiry (
COI) Implementation Unit on the status of governance reforms implemented up to the end of December 2022.
Skelton-Cline’s contracts with the government came under fire in the
COI report, with
COI Commissioner Sir Gary
Hickinbottom concluding that the contracts were patently false and demonstrated serious dishonesty on the part of public officials.
“On the evidence, there can be little if any doubt that these contracts were, on their face, false. They did not attempt to set out the intended contractual obligations of Mr Skelton Cline (if any),” Sir Gary found in his findings at the time.
According to the
COI Implementation Unit’s status report, the Auditor General also completed reports on HOA Assistance Grants and EZ Shipping’s government contracts for radar barges since 2019.
It is unclear if or when the reports will be made public, but the reports have since been submitted to Governor
John Rankin for consideration by the Auditor General, according to the
COI implementation Unit.
Statutory body reviews
In the meantime, two Independent Reviewers completed and submitted their reports on the establishment and maintenance of statutory bodies and their review of the membership of statutory boards.
These reviews will be submitted to Cabinet as ‘information papers’ and laid before the House of Assembly (HOA) before the relevant ministries begin public consultation and make changes to the relevant policies and procedures or request legislative amendments.
Director of the Unit Hadassah Ward has advised that work on 48 of the 50 Framework recommendations has begun, based on the timelines agreed in the Framework for Implementation of the Recommendations of the
Commission of Inquiry Report and Other Reforms.
According to Ward, “15 of the recommendations have been completed and 33 recommendations are in progress. The Recommendations are currently split into 132 actions. Of these, 52 (39%) are completed, 31 (23%) are in progress and on track, 26 (20%) are in progress but experiencing challenges and 22 (17%) have not been started as yet.”